Friday, January 28, 2005

Wrapping Up Week Three

Image Hosted by ImageShack.us

Image Hosted by ImageShack.us
Thursday Graham and Brad picked up the additional parts needed to finish venting the fireplace through the roof.

Image Hosted by ImageShack.us
And installed it of course.

Image Hosted by ImageShack.us
It looks like it is all but ready to go.

Image Hosted by ImageShack.us
They also finished insulating around the bookcase enclosures, and put up the vapor barrier.

Image Hosted by ImageShack.us
Friday the gas guy came to set up the pressure-test on the gas line.

Image Hosted by ImageShack.us
Monday the inspector will be here, then drywall!

Venting

Image Hosted by ImageShack.us
On Wednesday Brad stopped by the fireplace store to pick up some additional vent pipe, only to be told that the fireplace could not be vented as planned. The horizontal run was too long, by a foot and a half. Our only option was to vent through the roof. Oh, and now we have a gable vent where the fireplace would have vented. Not ideal, and if we had known this to begin with we may have planned the layout of the room differently, but thems the breaks. Not a huge deal in the overall picture.

Image Hosted by ImageShack.us
Also on Wednesday, they installed most of the fiberglass insulation on the knee-walls. There is just enough left open for the inspector to do his thing on Monday.

Image Hosted by ImageShack.us