Wednesday, January 26, 2005

Week the Third, Monday and Tuesday

Image Hosted by ImageShack.us
Monday.
Image Hosted by ImageShack.us
Brad and Graham put down most of the sub-floor.

Image Hosted by ImageShack.us
They also started framing for the shelves in the closet.

Image Hosted by ImageShack.us
Monday also saw witness to the arrival of the fireplace, and the framing of it's cabinet.

Image Hosted by ImageShack.us
Tuesday Brad and Graham got the rest of the sub-floor in place. Also, the insulation guys were here to scrape away the excess spray-foam.

Image Hosted by ImageShack.us
The floor is in for the cold storage behind the knee-wall.

Image Hosted by ImageShack.us
The box is complete for the closet shelves.

Image Hosted by ImageShack.us
The fireplace is fixed in place.

Image Hosted by ImageShack.us
And the vent has been cut through the north wall.

Image Hosted by ImageShack.us
More on the venting tomorrow...